N940AC Project Watch Update for Week of May 7, 2017

AVIONICS  

The wiring removal is complete with the exception of the environmental. New wiring has been installed in each wing for the magnetometers. All existing avionics equipment and racks have been removed. Installation drawings for the wiring are complete, the new wiring has been printed and wiring harness assembly has begun.

 

MAINTENANCE

Maintenance has removed the landing gear and it has been inspected, painted, and a partial re-assembly has begun. The environmental system mechanicals have been removed. The old fuel bladders have been removed. The inspection and replacement of the foam that is installed under each bladder is in work along with the installation of the new fuel cell bladders.

 

STRUCTURE

Structures have repaired the “Hood Formers” and are working the CK159-3 nose gear mount structural reinforcement.

 

REPAIRED NOSE GEAR

REPAINTED MAIN GEAR

REMOVED ACM

PANEL WIRING REMOVED

OLD FUEL BAG

NEW WIRING READY FOR HARNESS

NEW FOAM IN FUEL BAG CAVITY

GEAR INSPECTION AND REASSEMBLY

ENVIRONMENTAL REMOVED

AVIONICS EQUIPMENT REMOVED

AVIONICS REMOVED FROM NOSE

AVIONICS REMOVED FROM DRUM

 