N940AC Project Watch Update for Week of May 14, 2017

Maintenance 

Fuel cells continue to be installed.  NLG has been assembled and ready for installation.  CK159-3 has been completed.  Rudder torque tube has been removed, repaired and re-installed.  New baggage door seal has been installed.  Right MLG hinges have been replaced.  Enviro system air inlet scoop has been cut out and installed.

NOSE LANDING GEAR ASSEMBLY

CK159-K COMPLETED

NOSE LANDING GEAR

ENVIRO SYSTEM INLET AIR DUCT INSTALLED

RUDDER TORQUE TUBE

 