Project Watch

N940AC Project Watch

July 7, 2017
N940AC Project Watch Update for Week of July 2, 2017

This week we started and completed the inboard wing de-ice boot CK kit.  Horizontal leading edges arrived, have been fitted and drilled and are ready to be installed.  Started installing under floor insulation for cabin comfort system.  Avionics installed traffic box and continue to ring out wiring.

RIGHT INBOARD WING DEICE BOOT

LEFT INBOARD WING DEICE BOOT

UNDER FLOOR SOUNDPROOFING

HORIZONTAL LEADING EDGE

TRAFFIC BOX

 