N940AC Project Watch Update for Week of July 16, 2017

This week we finished up the under floor insulation and under floor ducts that needed replaced.  Floor panels are being prepped for re-installation.  Fuel leaks in wet wing area are being worked.  Enviro computers have been mounted, installed and wiring terminated.  Vertical repair has been completed per engineering drawing and de-ice boot has been installed.  In process of prepping horizontal boots for install.  Avionics equipment has been installed in nose area; in process of routing coax cables for antennas.  Instrument panel is being fitted and in process of being mounted.

 

ENVIRO COMPUTERS

VERTICAL LEADING EDGE

NOSE AVIONICS EQUIPMENT

INSTRUMENT PANEL

UNDER FLOOR INSULATION AND DUCTS

 