N840JK Project Watch Update for Week of October 29, 2017

This week we:

  • Finished primary and secondary control cable rigging
  • Sealed fuel leaks noted on 1st leak check and re-fueled aircraft for additional leak checks
  • Finished installing tail de-ice boots and wing de-ice boots (all surface de-ice boots are now installed)
  • Closed cabin floor and baggage floor panels
  • Installed exterior LED lighting package

Avionics:

  • Continue to upload software and operational checks of G950
  • All coax cables have been […]
    Posted in Uncategorized | No Comments |

N840JK Project Watch Update for Week of October 22, 2017

This week we continued installation of surface de-ice boots, installed left and right inboard wing boots, right and left horizontal boots and are in process of installing vertical boot.  Fuel cells and panels were all closed up and aircraft fueled for initial leak check; a few minor leaks were noted.  Aircraft was de-fueled and are in process of working fuel leaks.  Installed main landing […]

Posted in Uncategorized | No Comments |

N840JK Project Watch Update for Week of October 15, 2017

This week we finished up rigging of main flight controls, continued rigging of secondary flight controls, serviced nose landing gear and main landing gear, installed wheels and tires on main landing gear, received de-ice boots and are in process of prepping and installing.

Avionics has completed most ring outs for avionics wiring harness, are in process of fabricating and routing coax for […]

Posted in Uncategorized | No Comments |