N840JK Project Watch Update for Week of October 15, 2017

This week we finished up rigging of main flight controls, continued rigging of secondary flight controls, serviced nose landing gear and main landing gear, installed wheels and tires on main landing gear, received de-ice boots and areĀ in process of prepping and installing.

Avionics has completed most ring outs for avionics wiring harness, are in process of fabricating and routing coax for antennas and fabricating doublers and installing antennas.

RIGHT MAIN LANDING GEAR

RIGHT INBOARD WING DE-ICE BOOT

LEFT INBOARD WING PREPPED FOR DE-ICE BOOT

ANTENNA DOUBLER

AVIONICS ANTENNA

AVIONICS ANTENNA